Timeline
LEAP, phase by phase.
Key milestones from early works through program completion.
A 20-year program · 2025 – 2045

PAL 1 · 2025 – 2029
Foundation & Early Works
- Master Plan finalized (Dec 2025)
- Entrance roadway intersection (L1) design & construction
- Triturator and CRDC relocations
- Central Utility Plant expansion begins

PAL 2 · 2029 – 2034
Terminal & Apron Transformation
- Terminal Headhouse construction (T1)
- Terminal Apron reconfiguration (A1)
- Garage D opens (L3)
- General Use Building relocates (S1)

PAL 3 · 2034 – 2039
Concourse Expansion
- Terminal Concourse expansion completes (T2)
- RON / Deicing Apron operational (A2)
- ConRAC opens (L5)

PAL 4 · 2039 – 2045
Long-Term Capacity
- Remote Parking Facility (L4)
- Final landside refinements
- Program completion at full forecast capacity